Chasing light and building dreams - Solar thermal projects under construction | The scorching sun can’t stop our determination and responsibility
Time:2024-10-12
Three Gorges Energy Qinghai Golmud 100MW CSP Project EPC General Contracting
The total installed capacity of this project is 1100MW: 1000MW photovoltaic power generation project + 100MW solar thermal project. It is one of the sub-projects of the 1.6 million kilowatt photovoltaic thermal project in the Qinghai Haixi Base, located in the Wutumeiren Photovoltaic Thermal Park in Golmud City, Haixi Prefecture, Qinghai Province.

As of now, the reserved steel structure platform on the north side of the heat absorption tower has been installed, and the viewing platform outside the tower has been installed;
The installation of the heliostat has been nearly 96% completed, the excavation of the cable trench has been basically completed, and the cable laying is proceeding as planned;
The installation combination of the exhaust pipe of the air-cooled island has been completed by 10%;
The welding inspection of the cold and hot tank insulation hook has been basically completed.
SDIC Ruoqiang 100MW CSP project EPC general contracting project
The site of the 100MW solar thermal power generation project of SDIC Ruoqiang is located in Tiemulik Township, Ruoqiang County, Bayingolin Mongol Autonomous Prefecture, Xinjiang. It is about 205km away from Ruoqiang County in the northwest and about 62km away from Mangyaba, Qinghai in the northeast. The project will build a 1×100MW tower solar thermal power generation unit and configure an 8-hour molten salt heat storage system.


Up to now, the drilling and pouring of heliostat piles are proceeding in an orderly manner as planned, and nearly 80% has been completed; the expansion of the assembly workshop is progressing in an orderly manner.
Tangshan Haitai Solar Thermal + Photovoltaic Integration Project Tower Concentrating Solar Collector System
The scale of this project is 900MW photovoltaic + 100MW solar thermal. Shouhang is responsible for the production of heliostats, heliostat pile supply, air cooling equipment, and equipment above the large platform of the heat absorption tower.


As of now, 90% of the heliostat piles have been delivered;
50% of the air-cooled steel structures have arrived, and the remaining steel structures and equipment are being delivered in accordance with the schedule;
All equipment above the large platform of the heat absorption tower is under bidding and production.
Jinghe Xinhua New Energy 100MW CSP Project PC General Contractor
The project site is located in Jinghe County, Bortala Mongol Autonomous Prefecture, Xinjiang Uygur Autonomous Region. The project includes a 100MW tower molten salt solar thermal power station and a 900MW photovoltaic power station with a total installed capacity of 1GW.


On days when the sun is scorching, the front-line workers still stick to their jobs tenaciously, their clothes soaked with sweat like rain, but there is a light of determination shining between their brows, because they know that responsibility is more important than the scorching heat, because they understand that every minute of perseverance is a commitment to the team and is a key link to the success of the project.