Shouhang Hi-Tech won the bid for the EPC project of the steel structure intercooler tower of the 2×1000MW unit expansion project of Ningxia Power Liupanshan Power Plant
Time:2024-10-12
Recently, Shouhang Hi-Tech won the bid for the EPC project of steel structure intercooler tower for the 2×1000MW unit expansion project of Ningxia Power Liupanshan Power Plant initiated by State Energy Ningxia Liupanshan Energy Development Co., Ltd.

In the EPC project of steel structure intercooler tower for thermal power units in the expansion project of 2×1000MW units of Ningxia Power Liupanshan Power Plant, which won the bid this time, Shouhang Hi-Tech provided EPC general contracting for a complete set of steel structure intercooler towers and indirect air cooling systems for two units, including design, equipment supply, steel structure tower construction, commissioning, testing, management, inspection, completion, trial operation, defect elimination, formal operation, performance assessment and acceptance, technical and after-sales service, personnel training and the establishment of all engineering files that meet the requirements, etc., as well as all necessary materials, spare parts, special tools, consumables and related technical data.
Project Overview
The project is located in the New Materials Industrial Park in Guyuan City, Ningxia Hui Autonomous Region, with convenient transportation and well-connected roads around it.
The Guoneng Ningxia Liupanshan Power Plant is a remote expansion project with a construction scale of 2×1000MW single-reheat high-efficiency ultra-supercritical indirect air-cooled coal-fired units (with heating function), and desulfurization and denitrification devices are built simultaneously.
Planned start time: June 16, 2024
Planned completion time: August 30, 2026
This winning bid is of great significance. This project is the largest steel tower project won by Shouhang Hi-Tech so far, demonstrating the company's core competitiveness in the air cooling business. Shouhang Hi-Tech will continue to focus on the construction of clean energy and energy-saving and environmentally friendly ecological civilization, make bold assumptions and scientific demonstrations in practice, and achieve new breakthroughs in indirect cooling steel towers again and again.