Chasing Light and Building Dreams - Three Gorges Golmud | The Plant System Was Successfully Powered
Time:2024-11-11
At 19:16 on November 9, the Three Gorges Energy Golmud 100MW solar thermal EPC general contract project plant system was successfully powered.

The 110kV Liaoshen line, main transformer, plant high-voltage transformer and 6kV A and B sections of the plant power supply were successfully energized! The load capacitor was added to cooperate with the ground adjustment to complete the vector diagram measurement.
In order to ensure the success of the power supply to the plant, the test operation command organized a work deployment meeting before the power supply to the plant, and combined with the rectification content of the supervision and inspection of the power engineering quality supervision station, the power supply plan was fully checked. At the same time, in accordance with the preparation and review requirements of the standard operation ticket for power supply to the plant, the staff was organized to hold a briefing meeting on the operation process of the operation ticket to ensure that all staff were familiar with the operation.
Project Overview
This project is EPC contracted by a consortium consisting of Shouhang Hi-Tech, China Electric Power Engineering Consulting Group Northwest Electric Power Design Institute Co., Ltd., China Power Construction Group Sichuan Engineering Co., Ltd., and Shanghai Survey and Design Institute Co., Ltd.
The project is located in the Wutumeiren Solar Power Generation Base in Golmud City, Haixi Prefecture, Qinghai Province. The construction scale is 1×100MW molten salt tower solar thermal project. At the same time, a new 110kV booster station is built, which is connected to the 110kV side of the Heming 330kV collection station with a 110kV line. The absorber adopts Shouhang Hi-Tech's integrated absorber tube screen module, which greatly reduces the construction workload on the tower and can significantly shorten the construction period.

The successful completion of this important milestone of the project marks that the project construction has officially entered the subsystem commissioning stage, laying a solid foundation for the subsequent subsystem commissioning and the start-up of the entire unit. Shouhang Hi-Tech will continue to uphold the dream of "making the sky blue, the land green, the air clean, the water clean, and the people harmonious", work closely with all parties in the consortium, strictly perform the contract, and complete all tasks within the scope of the contract with high quality, contributing to the realization of the carbon peak and carbon neutrality goals!