First Flight Gaoke Signed Major Contract for Direct Air Cooling

Time:2023-01-13


Recently, Shouhang High-tech Energy Technology Co., Ltd. (hereinafter referred to as "the company" or "the seller") and Shanxi Installation Group Co., Ltd. (hereinafter referred to as "the buyer") signed the "Shanmeihequ 2 × 350MW Low Calorific Value Coal Power Generation Project" Direct Air Cooling System Equipment Purchase Contract ", the contract stipulates that the company will install Shanxi Province Group Co., Ltd.Shanmei Haqu 2 × 350MW low calorific value coal power generation project EPC general contracting project provides direct air cooling system equipment.

 

 

Subject of Contract

Direct air cooling system equipment;

Total Contract Amount (including tax)

RMB 117.33 million yuan (in words: one hundred and seventy-three hundred and thirty-three thousand yuan only);

Settlement Method

The payment is made in stages on a pro rata basis, as follows: the 3.1 advance payment is 10 per cent of the total contract price; the 3.2 completion payment is 60 per cent of the total contract price; the 3.3 acceptance payment is 20 per cent of the total contract price; and the 3.4 warranty is 10 per cent of the total contract price.

Effective Conditions

This contract shall take effect immediately after being signed by the legal representatives or authorized representatives of both parties and stamped with the special seal for the contract.

Contract Performance Period

From the effective date of the contract to the issuance of the last set of contract equipment "final acceptance certificate", and the buyer and seller of the debt relationship between the end of the end.