Chasing Light and Building Dreams—Three Gorges Golmud Chapter | The heat absorption tower was successfully capped
Time:2024-10-12
The 100MW solar thermal EPC general contracting project of Three Gorges Energy in Golmud, Haixi, successfully completed the capping of the heat absorption tower wall on March 18 after all the employees of the consortium project had gone through the baptism of extreme heat and cold and plateau.


The heat absorption tower is known as the "heart" of the entire solar thermal power station and is a vital component of the project. The successful capping of the heat absorption tower is also the second important node after the first mirror is offline. It marks an important node for the transition of the heat absorption tower civil construction to installation construction. The heat absorption tower building installation construction is the main line of the solar thermal power generation project. The completion of each node on schedule provides a guarantee for the overall progress of the project and creates conditions for subsequent installation construction.
Project Progress
The total installed capacity of this project is 1100MW: 1000MW photovoltaic power generation project + 100MW solar thermal project. It is one of the sub-projects of the 1.6 million kilowatt photovoltaic thermal project in the Qinghai Haixi base, located in the Wutumeiren photovoltaic thermal park in Golmud City, Haixi Prefecture, Qinghai Province.
So far, the bottoms of the cold and hot molten salt tanks have been installed, the beams of the cold molten salt tanks have been hoisted, and the tank tops have been installed and welded. The beams of the hot molten salt tanks have been installed, and the tank tops have been installed and cut.


This project is equipped with a large-capacity heat storage system, which can form a multi-energy complementary power generation mode with strong complementarity and good sustainability with volatile power sources such as photovoltaics and wind power, which will help the transformation and upgrading of the national energy structure and play its unique advantages in building a new power system with new energy as the main body.
Under the leadership of the consortium leader, the Shouhang Hi-Tech project team will work closely with all participating parties to strictly fulfill the contract and complete all tasks within the scope of the contract with high quality, ensure the 830 grid-connected power generation target, and let the Gobi Desert bloom giant "sunflowers" as soon as possible!