[Good News] Shouhang Energy Saving and Yumen Longteng Successfully Signed Yumen East Town Heat Transfer Oil Tank 50000 kW Photothermal Power Generation Demonstration Project!

Time:2019-10-17

Source:

Author:


On the afternoon of June 15, 2018, Beijing Shouhang Aiqiwei Energy Saving Technology Co., Ltd. and Yumen Longteng Xinneng Photothermal Development Co., Ltd. held a signing ceremony to sign the EPC General Contract Agreement for the 50000 kW Photothermal Power Generation Demonstration Project of Yumen Longteng Xinneng Photothermal Development Co., Ltd.

Leaders such as Huang Qingle, Vice Chairman of Shouhang Energy Conservation, Yang Rui, Deputy General Manager, Yu Ke, General Manager of Longteng Photothermal Company, and Shen Weiming, Deputy General Manager, attended the signing ceremony.

This is the second trough-type national photothermal demonstration power station project of the first voyage energy-saving general contract after the general contract of the 50MW trough-type photothermal demonstration power station of China General Nuclear Power Delingha Sun Island.

  

 

  

 

I. Introduction of the parties to the contract

1. Company Name: Yumen Longteng Xinneng Photothermal Development Co., Ltd;

2. Legal representative: Shen Weiming;

3. Registered capital: 10 million RMB;

4. Business scope: solar trough thermal power generation equipment, solar air conditioning equipment, solar heating system equipment, solar drying equipment, solar seawater desalination equipment, solar auxiliary crude oil extraction equipment, solar waste heat industrial salt production equipment R & D, production and sales.

5. Residence: No.24, Happiness Road, Jiuquan Circular Economy Industrial Park, Yumen City, Jiuquan City, Gansu Province;

6. There is no relationship between Yumen Longteng Xinneng Photothermal Development Co., Ltd. and the Company;

7, the most recent fiscal year Yumen Longteng New Energy Thermal Development Co., Ltd. and the Company did not have similar business;

8. Analysis of performance ability: The counterparty to this contract has good reputation and good performance ability.

II. Main Contents of the Contract

1. Subject matter of the contract: EPC general contracting project of Yumen Longteng Xinneng Photothermal Development Co., Ltd. Yumen East Town Heat Transfer Oil Tank 50000 kW Photothermal Power Generation Demonstration Project;

2. Total contract amount (including tax): 1,588.6 million yuan only (in words: one hundred and fifty-eight hundred and sixty-six million yuan only);

3. Settlement method: the 3.1 advance payment is 5% of the total contract price; 3.2 the first progress payment is 21.25 of the total contract price; 3.3 the second progress payment is 21.25 of the total contract price; 3.4 the third progress payment is 21.25 of the total contract price; 3.5 the fourth progress payment is 21.25 of the total contract price; the 3.6 acceptance payment is 10% of the total contract price.

4. Conditions for entry into force: the contract shall take effect after the signature and seal of the representatives of the parties;

5, the contract performance period: from the date of signing to the issuance of the "final acceptance certificate" and the payment of the two days.