Seawater, Brackish Water Desalination
Project Name: Shenhua Guohua Indonesia Java Seawater Desalination Project 2*4000 Tons/Day
Performance parameters
|
Name |
Parameters |
Name |
Parameters |
||||||||
|
daily output |
4000t/d |
Power consumption (within the desalination island) |
≤ 1.5kwh/m³ |
||||||||
|
design water production ratio |
10kg fresh water/kg steam |
Device output adjustable range |
50~110% |
||||||||
|
Product Water Quality (TDS) |
≤ 5mg/L |
Main equipment service life |
≥ 40 years |
Project Presentation
On August 1, 2019, the Shenhua Guohua Indonesia Java 7 2 x 4000 tons/day desalination project 2# machine, which was designed and supplied by the first flight of energy-saving, completed commissioning and successfully discharged water. After testing the operating indicators have reached the design requirements, the equipment running state is ideal. 2# machine completed commissioning marks the completion of the entire desalination project commissioning and put into operation.
Indonesia's Java No. 7 desalination project is the first desalination project for the first voyage to save energy, and it is also an overseas project to undertake the "Belt and Road. On August 1, 2019, the Shenhua Guohua Indonesia Java 7 2 x 4000 tons/day desalination project 2# machine, which was designed and supplied by the first flight of energy-saving, completed commissioning and successfully discharged water. After testing the operating indicators have reached the design requirements, the equipment running state is ideal. 2# machine completed commissioning marks the completion of the entire desalination project commissioning and put into operation.


Contact information
-
Email:shgk@sh-ihw.com
-
Fax:010-52256633
-
Add:Building 20,Block 3,188 South 4th Ring W.Rd,Fengtai,Beijing,China