Announcement on the signing of major contracts
Time:2023-12-06
Classification: Company Announcement
Recently, the consortium formed by Shouhang Hi-Tech Energy Technology Co., Ltd. and China Electric Power Construction Group Sichuan Engineering Co., Ltd. (hereinafter referred to as "the Company" or "Party B") and Jinghe Xinhua New Energy Co., Ltd. (hereinafter referred to as "Party A") signed the "Integrated Base Project of" Photothermal Energy Storage New Energy "of Jinghe Xinhua New Energy Co., Ltd.-Bid 7: PC General Contract for 100MW Photothermal Project". The contract stipulates that Party B is the general contractor of the "Photothermal Energy Storage New Energy" Integrated Base Project of Party A Jinghe Xinhua New Energy Co., Ltd.-Bid Section 7: 100MW Photothermal Project PC General Contracting Project, etc.
This contract belongs to the daily business behavior of the company. According to the company's "Articles of Association", this contract is signed after review and approval by the General Manager's Office. Now the relevant content announcement is as follows:
First, the counterparty introduction.
1. Company Name: Jinghe Xinhua New Energy Co., Ltd;
2. Legal Representative: Sun Dayong;
3. Registered Address: Room 303, 3rd Floor, No.8 Heping West Road, Jinghe County, Bortala Mongolian Autonomous Prefecture, Xinjiang;
4, business scope: licensing projects: power generation business, transmission business, power supply (distribution) business. (For projects that are subject to approval in accordance with the law, business activities can only be carried out after approval by relevant departments. The specific business projects are subject to the approval documents or license certificates of relevant departments.) General projects: technical services, technical development, technical consultation, technical exchange, technology transfer, Technology promotion. (With the exception of projects subject to approval in accordance with the law, business activities shall be carried out independently in accordance with the business license)
5. There is no relationship between Party A and the Company;
6. No similar business has occurred between Party A and the Company in the most recent fiscal year;
7. Analysis of performance ability: The counterparty to this contract is a large integrated company with good reputation and good performance ability.
II. Main Contents of the Contract
1. Subject matter of the contract: "Photothermal Energy Storage New Energy" Integration Base Project of Jinghe Xinhua New Energy Co., Ltd.-Bid Section 7: PC General Contract of 100MW Photothermal Project;
2. Total contract amount (including tax): RMB 1,259,500,000.00 (in words: one hundred and twenty-five thousand nine hundred and fifty thousand yuan only);
3, settlement method: phased according to the proportion of settlement.
4. Conditions of entry into force: This contract agreement shall take effect after being signed by the legal representatives or authorized representatives of all parties and stamped with the official seal of the unit respectively.
5. Term of performance of the contract: This contract agreement shall take effect after being signed by the legal representatives or authorized representatives of the parties and stamped with the official seal of the unit respectively. After the parties have fulfilled their obligations under the contract and paid the contract fees, the contract shall be automatically terminated.
6. Breach of Contract
(1) If the performance of the equipment is not up to standard, compensation shall be made according to the actual loss. If the quality of the project fails to meet the quality requirements, Party B shall unconditionally rework and rectify until it passes the acceptance, and Party B shall bear the responsibility for the delay of the construction period caused thereby; If the quality of the project still fails to meet the requirements of the contract after two acceptance checks, Party B shall pay Party A liquidated damages of 5% of the cost of the unqualified project, and Party A shall have the right to terminate the contract, at the same time, Party A has the right to entrust a third party to complete the project, and Party B shall bear the resulting expenses and responsibility for the delay of the construction period.
(2) If Party B fails to repair the project defects within a reasonable period of time during the defect liability period and warranty period, or refuses to repair as required by Party A, Party A has the right to entrust a third party to complete the project, and the risks and expenses arising therefrom shall be borne by Party B.
(3) Party B shall carry out safe and civilized construction, timely carry out safety production training and management for its labor service personnel, and provide and set up safety protection measures according to regulations. If Party B is punished by relevant departments due to safety accidents or non-compliance with the requirements of safe and civilized construction, Party B shall bear all economic and legal responsibilities, including but not limited to accident compensation, administrative fines and losses caused to Party A. At the same time, Party B is responsible for unconditional rectification in accordance with the requirements of relevant departments, Party A and the Supervisor. In case of suspension of work due to this, Party B is responsible for active coordination and rectification to meet the commencement conditions, and Party B shall bear all the risks and expenses arising therefrom.
(4) Party B shall pay the labor insurance and migrant workers' wage deposit within one month after entering the site. Party B shall not default on migrant workers' wages during construction. Before each payment, Party B shall provide a list of wages payable to workers and provide proof that all workers' wages have been settled within 7 days after payment. Otherwise, Party A has the right to postpone the payment, and Party B allows Party A to deduct migrant workers' wages from the project funds payable to Party B and pay them on behalf, party B shall bear all the economic and legal responsibilities arising therefrom. In case of any event or behavior that has a negative impact on Party A, such as migrant workers asking for wages or gathering the project department, Party B shall eliminate the impact within the time limit specified by Party A and pay the liquidated damages agreed in the contract.
(5) If Party B violates other requirements or commitments set in the bidding documents and causes losses to Party A, it shall be responsible for compensation.
(6) If the construction period is delayed due to Party B's reasons, it shall be implemented in accordance with Article 7.5.2 of the Special Contract. If the liquidated damages are not sufficient to make up for Party A's losses, Party B shall make up the compensation.
III. Impact of contracts on listed companies
1. The photothermal project signed this time belongs to the company's main business. The signing of this contract is the recognition of the company's technology, core equipment and general contracting capacity by the new energy photothermal power generation market. And the project is the national scenery heat (storage) integration base project, the implementation of the contract is conducive to the light hot melt salt as the energy storage end of the multi-energy complementary new energy as the main body of the new power system scale promotion. The signing of this contract is conducive to further enhancing the company's core competitiveness in the new energy solar thermal power generation market and has a positive impact on the company's medium and long-term development.
2, the company has the ability to perform the contract, capital, personnel, technology and production capacity, to ensure the smooth performance of the contract.
3. After the contract comes into effect, the delivery equipment and the implementation of the project shall be arranged according to the schedule of the project, and the specific schedule shall be performed according to the time agreed in the contract and technical agreement. The total contract amount (including tax) accounts for about 193.11 of the company's operating income of 652,205,492.85 yuan in 2022. The implementation of the contract will enhance the company's operating income and operating profit in 2023 and 2024.
4, the signing and performance of this contract does not affect the company's business independence. There is no reliance on the other party to the contract as a result of the performance of the contract.
IV. Risk Tips
1, the contract performance cycle is long, there is a risk that the contract can not be performed due to the impact of force majeure risk.
2, the contract payment recovery in stages according to the proportion of implementation, due to the long performance cycle, there is a risk of slow payment recovery, please pay attention to the risk of investors.
3. Steel and glass are the main raw materials of the company's products. The performance cycle of this contract and the production cycle of the product are long, and the operating cost is affected by the price changes of steel and glass during the production cycle. Fluctuations in the price of raw materials may have a favorable or adverse effect on the Company's gross profit amount, thus exposing the Company to the risk of fluctuations in gross profit margin due to fluctuations in the price of raw materials.
V. Contract Review Procedure
This contract is a day-to-day business conduct of the Company and does not require the approval of the Board of Directors of the Company, nor does it require the opinions of independent directors and lawyers.
VI. Documents for Reference
1. The original contract signed by the parties.
It is hereby announced.
Shouhang Gaoke Energy Technology Co., Ltd.
Board of Directors
December 5, 2023