Shouhang High-tech Energy Technology Co., Ltd. (hereinafter referred to as "the company" or "Shouhang High-tech") and China Power Engineering Consulting Group North China Electric Power Design Institute Co., Ltd. (hereinafter referred to as "North China Institute"), China Energy Construction Northwest City Construction Co., Ltd. (hereinafter referred to as "Northwest City Construction") formed a bidding consortium, participated in the Shanghai Electric Power Co., Ltd. Xinjiang Hami North 100000 kW Photothermal Power Generation Project EPC general contract bidding, on December 23, 2022, we received the "Notice of Winning Bid" (Notice of Winning Bid No. SH2022122301) of the project, confirming that the bidding consortium won the bid for the EPC General Contracting Project of Shanghai Electric Power Xinjiang Hami North 100000 kW Photothermal Power Generation Project. Now the relevant content announcement is as follows:
I. Contents of Letter of Acceptance
The tender documents submitted by you for the 30th batch of Shanghai Electric Power 2022 tender for the EPC general contract section of the 100000-kilowatt photothermal power generation project in Hami North, Xinjiang, have been accepted by us and have been identified as the winning bidder (bid winning notice No. SH2022122301).
Bid price: RMB 1216.077632 million.
Duration (delivery date): calendar days to meet the requirements of bidding and procurement.
Quality standard: meet the requirements of bidding and procurement.
Please contact the tenderer to sign the contract within 5 working days.
Second, the winning project division of labor and the impact on the company.
1. In the EPC general contracting project of Shanghai Electric Power Xinjiang Hami North 100000 kW Photothermal Power Generation Project, according to the division of labor of the consortium, Shouhang High Tech will take the lead in the EPC general contracting management of the Photothermal Power Generation Project and provide the EPC and power equipment procurement of Sun Island. North China Institute is responsible for the overall design and survey of the project; Northwest Urban Construction is responsible for the construction and installation of power island. The procurement scope of detailed division of labor and equipment shall be negotiated separately after the project is signed.
2. The winning CSP project belongs to the company's main business. According to the progress of the project, the subsequent signing of formal business contracts and smooth implementation will have a positive impact on the company's future market development and business performance. The implementation of the above winning project will not affect the independence of the company's business.
Third, the project won the bid risk tips.
As of the date of this announcement, the project has not yet signed a formal business contract, and there is still uncertainty in the implementation of the project. The final implementation of the project is subject to the terms of the formal contract. The company will fulfill the obligation of information disclosure in a timely manner according to the follow-up progress of the project. Please the majority of investors to pay attention to investment risk.
IV. Documents for Reference
1. Letter of Acceptance.
It is hereby announced.