Announcement on the signing of major contracts
Time:2022-11-16
Classification: Company Announcement
Recently, a consortium composed of Shouhang High-tech Energy Technology Co., Ltd., China Power Engineering Consulting Group Northwest Electric Power Design Institute Co., Ltd., China Power Construction Group Sichuan Engineering Co., Ltd., and Shanghai Survey and Design Institute Co., Ltd. (hereinafter referred to as the "Company" or "Contractor") and Three Gorges Energy Qinghai Golmud Power Generation Co., Ltd. (hereinafter referred to as "Employer") signed the EPC General Contract for Three Gorges Energy Qinghai Golmud 100MW Photothermal Project. The contract number is 63036202. The contract stipulates that the contractor is the general contractor of the "Three Gorges Energy Qinghai Golmud 100MW Photothermal Project EPC General Contract" project.
This contract belongs to the daily business behavior of the company. According to the company's "Articles of Association", this contract is signed after review and approval by the General Manager's Office. Now the relevant content announcement is as follows:
First, the counterparty introduction.
1. Company Name: Three Gorges Energy Qinghai Golmud Power Generation Co., Ltd;
2. Legal representative: Chen Yongming;
3. Domicile: No.1 Photovoltaic Road, East Exit Photovoltaic Park, Golmud City, Qinghai Province;
4. Business scope: permitted items: power generation business, power transmission business, power supply (distribution) business; hydropower; installation, maintenance and testing of power transmission, power supply and power receiving facilities (projects subject to approval according to law can only be carried out after approval by relevant departments, and the specific business projects shall be subject to the approval results). General items: technical services, technology development, technical consultation, technology exchange, technology transfer, technology promotion; power generation technology services; investment activities with its own funds (except for projects that must be approved in accordance with the law, business activities are carried out independently in accordance with the law with a business license).
5, the contractor and the company does not have an associated relationship;
6. No similar business has occurred between the contractor and the Company in the most recent fiscal year;
7. Analysis of performance ability: The counterparty to this contract is a large integrated company with good reputation and good performance ability.
II. Main Contents of the Contract
1, the subject of the contract: Three Gorges Energy Qinghai Golmud 100MW solar thermal project EPC general contract;
2. Total contract amount (including tax): RMB 1,648,010,207.00 yuan (in words: 1.60 billion yuan only);
3, the scope of the contract: EPC general contract; station operation and maintenance; survey and design; engineering construction, equipment, materials and materials supply; construction, commissioning, operation and maintenance and acceptance scope; scientific research project research costs and requirements.
4, settlement method: phased according to the proportion of settlement.
5. Conditions of entry into force: This contract shall be signed by the legal representatives or authorized representatives of the parties and shall enter into force at the same time as the project contract after being stamped with the official seal of the unit.
6. Term of performance of the contract: from the effective date of the contract until the completion and acceptance of all works and the settlement of the creditor's rights and debts between the contractor and the contractor.
7. Breach of Contract
7.1 the circumstances of the contractor's breach of contract
Any of the following circumstances occurring during the performance of the contract shall be a breach of contract by the Contractor;
(1) The design of the contractor, the contractor's documents, the implementation and completion of the project does not comply with the law and the contract;
(2) The Contractor, in violation of Article 1.8 or Article 4.3, privately transfers all or part of the rights under the contract to another person, or privately transfers all or part of the obligations under the contract to another person;
(3) The Contractor, in violation of the provisions of Clause 6.3 or 7.4, withdraws the construction equipment, temporary facilities or materials that have entered the construction site as agreed in the contract from the construction site without permission and with the approval of the Supervisor;
(4) The Contractor uses unqualified materials or engineering equipment in violation of the agreement in Article 6.5, and the quality of the project does not meet the standard requirements, and refuses to remove the unqualified project;
(5) The contractor fails to complete the work agreed in the contract in time according to the contract schedule, resulting in delay of the construction period;
(6) Failing to pass the completion test or the post-completion test due to the reasons of the Contractor;
(7) During the defects liability period, the Contractor fails to repair the contents of the defects list listed in the project acceptance certificate or the defects occurred during the defects liability period, and refuses to repair according to the instructions of the Supervisor;
(8) The Contractor is unable to continue to perform or clearly indicates that it will not perform or has substantially stopped performing the Contract;
(9) Other circumstances in which the Contractor fails to perform its obligations as agreed in the contract.
7.2 Treatment of Contractor's Breach of Contract
(1) In the event of a breach of contract as stipulated in Item 22.1.1(6), the Contractor shall compensate for the damage caused by the failure to pass the completion/post-completion test as required by the Employer. In the event of an extension, the Contractor shall be liable for the extension.
(2) In the event of a breach of contract as stipulated in Item 22.1.1(8), the Employer may notify the Contractor to terminate the contract immediately and deal with it in accordance with Items 22.1.3, 22.1.4 and 22.1.5.
(3) In case of any breach of contract by the Contractor other than those stipulated in Item 22.1.1(6) and Item 22.1.1(8), the Supervisor may issue a rectification notice to the Contractor and require him to make corrections within the specified time limit. Unless otherwise agreed in the terms of the contract, the contractor shall bear the cost increase and (or) delay of the construction period caused by its breach of contract.
7.3 to terminate the contract due to the contractor's breach of contract
If the Contractor still fails to correct the breach 28 days after the Supervisor issues the rectification notice, the Employer shall have the right to terminate the Contract and issue a notice of termination to the Contractor. Within 14 days after the Contractor receives the contract termination notice from the Employer, the Contractor shall withdraw from the site, and the Employer shall send personnel to the construction site to complete the site handover procedures, and the Employer shall have the right to organize personnel or entrust other contractors. The Employer shall have the right to detain and use the Contractor's materials, equipment and temporary facilities on the Site for the need to continue to complete the Project. However, this action of the contractor does not exempt the contractor from the liability for breach of contract, nor does it affect the contractor's right to claim compensation under the contract.
III. Impact of contracts on listed companies
1. The photothermal project signed this time belongs to the company's main business. The signing of this contract is the recognition of the company's technology, core equipment and general contracting capacity by the new energy photothermal power generation market. And the project is the national scenery heat (storage) integration base project, the implementation of the contract is conducive to the light hot melt salt as the energy storage end of the multi-energy complementary new energy as the main body of the new power system scale promotion. It has a positive impact on the company's medium-and long-term development.
2, the company has the ability to perform the contract, capital, personnel, technology and production capacity, to ensure the smooth performance of the contract.
3. After the contract comes into effect, the delivery equipment and the implementation of the project shall be arranged according to the schedule of the project, and the specific schedule shall be performed according to the time agreed in the contract and technical agreement. The total contract amount (including tax) accounts for about 229.36 of the company's operating income of 718,536,068.30 yuan in 2021. The implementation of the contract will enhance the company's operating income and operating profit in 2022 and 2023.
4, the signing and performance of this contract does not affect the company's business independence. There is no reliance on the other party to the contract as a result of the performance of the contract.
IV. Risk Tips
1, the contract performance cycle is long, there is a risk that the contract can not be performed due to the impact of force majeure risk.
2, the contract payment recovery in stages according to the proportion of implementation, due to the long performance cycle, there is a risk of slow payment recovery, please pay attention to the risk of investors.
3. Steel and glass are the main raw materials of the company's products. The performance cycle of this contract and the production cycle of the product are long, and the operating cost is affected by the price changes of steel and glass during the production cycle. Fluctuations in the price of raw materials may have a favorable or adverse effect on the Company's gross profit amount, thus exposing the Company to the risk of fluctuations in gross profit margin due to fluctuations in the price of raw materials.
V. Contract Review Procedure
This contract is a day-to-day business conduct of the Company and does not require the approval of the Board of Directors of the Company, nor does it require the opinions of independent directors and lawyers.
VI. Documents for Reference
1. The original contract signed by the parties.
It is hereby announced.
Shouhang Gaoke Energy Technology Co., Ltd.
Board of Directors
November 15, 2022