Announcement on the Signing of Investment Cooperation Agreement with the People's Government of Suzhou District, Jiuquan City
Time:2022-08-04
Classification: Company Announcement
I. Overview of Agreement Signing
1. Shouhang Hi-Tech Energy Technology Co., Ltd. (hereinafter referred to as the "Company", "Party B" or "Shouhang Hi-Tech") and the People's Government of Suzhou District, Jiuquan City (hereinafter referred to as "Party A") recently signed the "Investment Cooperation Agreement".
2. The Investment Cooperation Agreement does not constitute a connected transaction, nor does it constitute a major asset reorganization as stipulated in the measures for the Administration of Major Asset reorganization of listed companies.
3. The 28th meeting of the fourth board of directors of the company deliberated and passed the "Proposal on Signing an Investment Cooperation Agreement with the People's Government of Suzhou District, Jiuquan City". The proposal was approved by 9 votes, 0 votes against, and 0 abstentions.
4. After the investment project mentioned in the Investment Cooperation Agreement is approved, the company will introduce central enterprises and state-owned enterprises as strategic investors according to the investment needs of the project, and determine the specific proportion. If the investment amount meets the criteria for consideration by the shareholders' meeting, the company will hold a shareholders' meeting at that time to consider it and disclose it in accordance with the relevant provisions of the CSRC and the exchange.
Main contents of 2. investment cooperation agreement
(I) investment project
200MW molten salt tower-type thermal energy storage power generation project, at the same time in the jurisdiction of Jiuquan City to configure 800MW wind power 520MW photovoltaic. The final implementation of the filing project is "200MW photothermal 800MW wind power 520MW photovoltaic" photothermal (storage) new energy multi-energy complementary integration of large base project.
(II) Investment Scale
"200MW photothermal 800MW wind power 520MW photovoltaic" photothermal (storage) new energy multi-energy complementary integration of large base project, the estimated investment amount of about 10 billion to 11 billion. According to the agreement, Party B has the right to introduce suitable central enterprises and state-owned enterprises to jointly develop the project according to the specific scale of project investment.
(III) rights and obligations of Party A
1. After Party B applies for filing, Party A shall go through the filing formalities with Party B, and appoint special personnel to assist Party B in handling the preliminary work formalities such as planning, land use, water and soil conservation, environmental protection, forest land, ore pressing, etc., so as to improve the efficiency of various preliminary work. Both parties strive to complete the preliminary formalities of the project before March 30, 2023.
2. In order to ensure the economy of this project, Party A is responsible for applying to the Jiuquan Municipal People's Government to implement the ratio of "1 (solar thermal):4 (wind power):2.6 (photovoltaic)" to allocate wind power and photovoltaic indicators of wind power base within the jurisdiction of Jiuquan City for this project.
3. Party A does not participate in Party B's production and operation management and other activities, but has the right to supervise and guide Party B's project construction progress, safe production, ecological environment protection, etc.
4. Party A actively cooperates with Party B in the site selection of the project, and the land cost of the construction project shall be paid by Party B in accordance with laws, regulations and national policies.
5. Party A shall provide project approval support and convenient approval services for Party B's project construction, and the expenses shall be borne by Party B.
6. Party A actively strives for national and local preferential policies for Party B's project construction coordination.
7. Party A shall create a good investment environment for Party B and actively coordinate and deal with the difficulties and problems in the construction process of Party B.
(IV) Rights and Obligations of Party B
1. Within 20 working days after the signing of this Agreement, Party B shall set up a project company or determine a responsible company in Suzhou District as the main body of the implementation of the project.
2. Within 30 working days after the Jiuquan Municipal People's Government allocates full wind power and photovoltaic indicators for the project, Party B shall ensure that the project starts and connect to the grid for power generation within 2 years after the start of construction.
3. Party B shall apply for project filing within 5 working days after the establishment of the main body of the project company.
4. Party B has the right to independently introduce suitable central enterprises and state-owned enterprises as strategic investors to participate in the investment of the project in accordance with the law.
5. Party B must register an independent legal entity at Party A's location to operate and manage this project, and pay taxes in accordance with regulations.
6. After the project is completed and put into production, Party B shall give priority to hiring qualified local personnel and strictly implement the national labor security laws and regulations.
7. After Party B signs this Agreement, it must invest in the construction in full in accordance with the project investment plan to ensure that the project is completed and put into production on schedule.
8. Party B's construction projects must go through the procedures of safety reporting, quality supervision, planning permit, construction permit, etc. in accordance with the law, and implement safety measures to ensure construction safety.
9. Party B must use the land in accordance with the provisions of the Land Transfer Contract, and shall not change the use of the land during the operation period, and shall not transfer the land without authorization.
III. Impact of the Agreement on Listed Companies
The company has been actively promoting the development of new energy resources based on photothermal power generation and energy storage technology for many years. Jiuquan, Gansu has a good location advantage and rich new energy resources. This cooperation will further promote the company's new energy in Jiuquan City. Coordinated development of the resource development sector in the field. At the same time, the company will rely on Jiuquan City as the base point, to the northwest more abundant regional layout to photothermal power generation, energy storage technology-based new energy business.
If the projects mentioned in the investment cooperation agreement signed this time are approved and implemented normally, the implementation of the project will have a positive impact on the company's future performance. The performance of this agreement will not affect the independence of the company's business.
IV. Risk Tips
1. The project mentioned in the investment cooperation agreement has not been approved, and there is still some uncertainty as to whether it can be approved for filing. In the future, the company will disclose the progress of the project in a timely manner according to the approval.
2. In case of changes in relevant national and Jiuquan policies or changes in project implementation conditions during the implementation of this investment project, the project implementation plan will also be adjusted and changed if both parties agree in writing. Investors are kindly requested to pay attention to investment risks.
3. The total amount of investment is relatively large, and there is a certain degree of uncertainty about whether the project funds and investors can be in place on schedule. Please the majority of investors to pay attention to investment risk.
V. Documents for Reference
1. Investment Cooperation Agreement signed between the Company and the People's Government of Suzhou District, Jiuquan City.
It is hereby announced.
Shouhang Gaoke Energy Technology Co., Ltd.
Board of Directors
August 3, 2022